|
Evaluation Process The project team developed an evaluation process to help develop the Long-Term Vision (Preferred Strategy). The process begins with the scoping process, which the team collects and identifies the transportation issues throughout the corridor. The evaluation criteria is then developed. Once the criteria is developed, then alternatives are brainstormed for each corridor. The alternatives go through a three level evaluation process in which Long-Term Vision is developed. Alternatives Evaluation Criteria Based on the scoping process, Project Issues have been identified for the South I-25 Corridor and US 85 Corridor. These issues combined with the project problem statement became the basis of developing the project objectives. The alternatives evaluation criteria were developed from the project objectives (see figure below). Criteria Development Chart Alternatives Evaluation Process The issues collected from the public and local agencies may be sorted into five categories: mobility, safety, environmental, implementation, and community values. Criteria for each level of the evaluation process was developed based on these categories. The following table is a matrix showing the criteria used in this three-step process. |
| Category | 1. Eliminate Unrealistic Alternatives
|
2. Evaluation of Alternatives Mode and Corridor
|
3. Evaluation of Packages by Corridor
|
| Mobility |
|
||
| Safety |
|
||
| Environmental |
|
|
|
| Implementation | |||
| Community Values |
|
|
The intent of the first level of evaluation is to eliminate alternatives from consideration that are clearly unsuitable or do not meet the goals and objectives of the project. The entire list of alternatives developed are evaluated by the following yes or no questions to eliminate unrealistic alternatives:
IF THE ANSWER TO ONE OF THE ABOVE QUESTIONS IS NO THEN THE ALTERNATIVE IS ELIMINATED FROM FURTHER CONSIDERATION Alternatives for Evaluation
The South I-25 Corridor and US 85 Corridor EIS is evaluating a range of reasonable alternatives that address the purpose and need of the project. The Long-Term Vision is developed through a multi-modal approach, and will likely be a combination (2 or more) of highway, transit, transportation management, and/or enhancements. Based on input from the Project Team, Issues Team, and stakeholders; lists of alternatives for I-25 and US 85 were developed. These alternatives were sorted into the following categories for each corridor:
Alternatives remaining after first level of evaluation
The following alternatives survived the first level of evaluation and has proceeded into the second level:
Results of 2nd Level Evaluation The second level evaluates the remaining alternatives that survived the first screening level of evaluation for each corridor. These alternatives are compared within each mode and rated against each other by criteria. A rating system is used that categorizes each alternative as least favorable, moderately favorable, and most favorable for each category based on the criteria. The alternatives that best meet the criteria and purpose can then be combined with alternatives from other modes to form packages that will be evaluated in the third level. I-25 Ratings |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Mobility | Environmental | Implementation | Community Values | ||||
| Travel Time between Origin & Destination | Amount of New ROW Required | Number of Disturbed Acres | Ease of Construction | Capital Costs (per mile) | Community/ Agency support | Ease of Use | |
| NO-ACTION ALTERNATIVE | |||||||
| HIGHWAY | |||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
| FIXED GUIDEWAY | |||||||
|
|||||||
|
|||||||
|
|||||||
| RUBBER-TIRED TRANSIT | |||||||
|
Varies by Highway Alternative | Varies by Highway Alternative | Varies by Highway Alternative | Varies by Highway Alternative | Varies by Highway Alternative | ||
| TRANSPORTATION MANAGEMENT | |||||||
|
|||||||
|
|||||||
|
|||||||
|
See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | ||||
|
See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | ||||
|
See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | ||||
|
See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | ||||
|
See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | |||||
|
See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | See Hwy Rating #4,#5 | ||||
| ALTERNATE ROUTES | |||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
FOOTNOTES:
NOTE:
TRAVEL TIMES OF ALTERNATE ROUTES CANNOT BE COMPARED TO EACH OTHER
GENERAL NOTE: THE ASSUMPTIONS USED FOR THESE CRITERIA ARE ONLY FOR THE SECOND LEVEL EVALUATION. MORE DETAILED ANALYSIS AND REFINEMENT OF THE ASSUMPTIONS WILL BE REQUIRED IN THE THIRD LEVEL EVALUATION. US 85 Ratings |
Mobility |
Environmental |
Implementation |
Community Values |
|||||||||||
Travel Time between Origin & Destination |
Amount of New ROW Required |
Number of Disturbed Acres |
Ease of Construction |
Capital Costs (per mile) |
Commun |
Ease of Use |
||||||||
NO-ACTION ALTERNATIVE |
||||||||||||||
|
HIGHWAY |
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
| FIXED GUIDEWAY | ||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
| RUBBER-TIRED TRANSIT | ||||||||||||||
|
Varies by Hwy Alternative |
Varies by Hwy Alternative |
Varies by Hwy Alternative |
Varies by Hwy Alt. |
Varies by Hwy Alt. |
|||||||||
TRANSPORTATION MANAGEMENT |
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
||||||||||||||
ALTERNATE ROUTES |
||||||||||||||
|
||||||||||||||
|
||||||||||||||
|
FOOTNOTES:
3. EXTEND QUEBEC TO CASTLE PINES PARKWAY. START: PLUM CREEK PARKWAY END: C-470 / QUEBEC
4. EXTEND US 85. START: PLUM CREEK PARKWAY END: C-470 / US 85
GENERAL NOTE:
THE ASSUMPTIONS USED FOR THESE CRITERIA ARE ONLY FOR THE SECOND LEVEL EVALUATION. MORE DETAILED ANALYSIS AND REFINEMENT OF THE ASSUMPTIONS WILL BE REQUIRED IN THE THIRD LEVEL EVALUATION. Packages for Evaluation Packages for improvements to I-25 and US 85 were developed using the results of the Second Level Evaluation: Evaluation of Alternatives by Mode and Corridor, with consideration of public input, cost-effectiveness, compatibility of the elements, and other issues. These packages do not represent the Long-Term Vision (Preferred Strategy). They were developed for the purpose of testing concepts and combinations of alternatives. The results of the evaluation of these alternatives will be used to refine these packages or combine them into another package to be developed into the Long-Term Vision.
All of the packages include the Early-Action Projects. The Early-Action Projects are safety improvement projects that have been previously approved through separate studies and environmental clearances. These projects are either in the design phase or construction phase.
In addition to these projects, Douglas County and Town of Castle Rock have committed to roadway improvements. Typically these improvements address local needs and deficiencies.
The third level of evaluation analyzes the improvement packages against each other. The results of this level will be used to develop the Long-Term Vision, which will include two separate plans (one for I-25 and one for US 85). Results of 3rd Level Evaluation
The third level of evaluation analyzes the packages that were developed as part of the second level of evaluation. This level is more detailed and challenging than the first two levels. The values developed will be for comparison purposes only and will be refined as the Long-Term Vision is developed. The criteria are as follows:
Compatibility Table The Compatibility Table is used to illustrate what packages are compatible with each other. Packages were eliminated for the following reasons:
The compatibility chart identifies the package compatibility: After the completion of the third level of evaluation, the South I-25 Corridor and US 85 Corridor limits were extended to include the I-25 roadway between Lincoln Avenue and C-470. The Long-Term Vision has been updated to show the addition of a general purpose lane to the C-470 Interchange. View the South I-25 Long-Term Vision for South I-25 & US 85 through 2020 & Beyond:
Click to view enlargement!
Last Updated: 07.07.2008 04:13 PM This is a Colorado Department of
Transportation |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||