Schedule
Conceptual Design Phase
The Titan Road Improvement Project began in the Spring of 1999. The conceptual design phase of the project was completed early in 2000.
Preliminary Design Phase
After determining a feasible design solution, CDOT began preliminary design in the Spring of 2000. During this phase CDOT will conducted studies, obtained clearances, and determined the need for any mitigation measures.
Traffic Noise Analysis was completed during this phase.
Final Design Phase
Final plans were prepared with the final design stage completed as scheduled in June 2001.
Contractor
Selection
SEMA
Construction, Inc. of Englewood, Colo. was selected as the construction
contractor for the project, following advertisement of the job during summer
2001. SEMA Construction is on track
to complete construction by June 2003.
Construction
(Current Phase!)
Construction
of the Titan Road Improvement project is under way with dirt hauling operations
preparing the project site. As the
project progresses, new grade-separated bridges on Titan Road will cross over
Burlington Northern Santa Fe and Union Pacific Railroad tracks to eliminate
vehicle/train accidents. A new
four-ramp diamond interchange will be constructed at US 85 following a northern
realignment of Titan Road (see Project Description page for further
detail).
Other
construction elements include construction of local access roads connecting
Titan Road with Titan Park Circle, Titan Court and area businesses.
On the east side of US 85, Wildfield Lane also will be realigned and
extended to the north to connect with Titan Road.
|