Schedule

Conceptual Design Phase  

The conceptual design phase has been completed.

Preliminary Design Phase  

The preliminary design phase has been completed.

Final Design Phase  

The Wolfensberger Interchange Project has been proceeding through the final design phase and the project was ready for a Final Office Review (FOR) on September 28, 2000. After the FOR, plans were completed and packaged with specifications for bid. The final design phase of the Wolfensberger Interchange Project was complete in Late 2000.

Advertisement  

Public advertisement for the construction contract was scheduled for July 2001 when construction contractor bids were opened and the job was awarded to Lawrence Construction, the prime contractor on the project.  

Construction  

Construction of the Wolfensberger Interchange began on October 3, 2001 with the closing of the southern half of the structure. Eastbound traffic has been redirected to the inside westbound lane. This allows traffic to continue to travel in both directions across the bridge. This traffic configuration will remain consistent throughout the course of the project.

Currently, CDOT is working to reconstruct the Wolfensberger Bridges over I-25 and Plum Creek.  Caissons were drilled at Plum Creek and I-25 and abutments were backfilled in January 2002 in advance of bridgework.  Pier cap falsework progress is underway and construction of a new CDOT maintenance facility will continue through February.  With cooperative weather, all work should be completed in July of 2002.

Last Updated: 07.07.2008 04:13 PM