Schedule
Conceptual Design Phase
The conceptual design phase has been completed.
Preliminary Design Phase
The preliminary design phase has been completed.
Final Design Phase
The Wolfensberger Interchange Project has been proceeding through the final design phase and the project was ready for a Final Office Review (FOR) on September 28, 2000. After the FOR, plans were completed and packaged with specifications for bid. The final design phase of the Wolfensberger Interchange Project was complete in Late 2000.
Advertisement
Public advertisement for the construction contract was scheduled for July 2001 when construction contractor bids were opened and the job was awarded
to Lawrence Construction, the prime contractor on the project.
Construction
Construction of the Wolfensberger Interchange
began on October 3, 2001 with the closing of the southern half of the structure. Eastbound traffic
has been redirected to the inside westbound lane. This allows traffic to
continue to travel in both directions across the bridge. This traffic
configuration will remain consistent throughout the course of the project.
Currently, CDOT is
working to reconstruct the Wolfensberger Bridges over I-25 and Plum Creek.
Caissons were drilled at Plum Creek and I-25 and abutments were backfilled in
January 2002 in advance of bridgework. Pier cap falsework progress is underway
and construction of a new CDOT maintenance facility will continue through
February.
With cooperative weather, all
work should be completed in July of 2002.
|
||
|